Police Station Project Updates
NOTE THAT THE AVON POLICE DEPARTMENT IS NOW LOCATED AT 86 FAGAN DRIVE.
- View May 17, 2019 update recorded by ACAM
- View October 8, 2018 update recorded by ACAM
- View Photo Updates
- Watch the Groundbreaking Ceremony - July 2018
- Watch the Informational Meeting - May 2018
- Police Department Project Partners Information
- View the General Contractor Bid Tabulation
View Current updates below:
June 2019
Current Status: work continues on the preliminary punch list and finish work. Coordination of the Police department move is ongoing.
Are we on time: No. The contractor is behind in wrapping up the building. The Police Department is scheduled to move into the building the week of July 22nd, with an E911 switchover about a week later.
Are we on budget: Yes
Next Steps: Once substantial completion is achieved; one final punch list will be issued. Coordination of the move in and E911 switchover are slated to be complete by the first week in August.
May 2019
Current Status: A preliminary punch list was generated. Finish work and landscaping is still ongoing. Coordination of E911 and moving the Police Department into the building has begun.
Are we on time: No, contractor appears to be about 30 days behind schedule.
Are we on budget: Yes
Next steps: Coordination of E911 and moving dispatch from the current building to this one are being coordinated with all parties. Finish work (hardware installation etc) is ongoing and work has begun on a preliminary punch list.
April 2019
Current Status: The work is wrapping up! The finish work inside the building including flooring, painting, hardware installation, delivery and installation of the Dispatch consoles continues. Electrical, HVAC and plumbing work inside the building is ongoing. Procurement of furniture has been completed. Coordination of delivery is being scheduled.
Are we on budget: Yes
Next steps: Substantial completion is set for the end of the month. The OPM, GC and Design team are working on the finish elements in an effort to get the occupancy permit and begin the move in.
March 2019
The Carport concrete was poured, as well as the concrete for the jail cell beds and booking room benches. The wall protection, metal stud jail ceilings, gypsum board in the sally port, the overhead doors, the armory bullet proof door, casework and exterior ventilation louvers were all installed. The sally port and garage interior north wall were insulated. The store front system at the front vestibule was installed. The epoxy floors were completed, and the floors are being prepped for the VCT flooring and the carpet was delivered. Most walls have at least one coat of paint. Sinks were installed. The Building Management System controls to the roof top units were connected. Grills, diffusers and louvers in ceilings were installed. The exit signs, fire alarms, occupancy sensors, lighting, camera conduit in jail cells and booking were completed as well as underground conduit and tagged wall plates. The Generator was started, tested by manufacturer representative and observed by the commissioning agent. Excavation and grading began at parking lot.
Are we on time? Yes
Are we on budget? Yes
Next Steps: Work continues on the interior and exterior of the building. The committee is working with ACG and Chief Bukunt on FF&E procurement items
February 2019
Installation of the gypsum board walls, bullet resistant panels, security mesh at ceilings and walls, the acoustical ceiling grid, attic stairs, window trim and casework were complete as well as sally port gypsum walls and ceiling. The pitch pockets and flashing for roof penetrations were completed. The duct work and exterior walls were insulated. Painting began and windows and door frames were caulked. The dry valve assembly and compressor for carport dry sprinkler system as installed. Columbia gas installation is completed. The male and female shower units and hot water heater was completed, and the Water Department turned on the domestic water supply to the building. Lighting and exterior lighting was installed. The water heater and recirculation pump, septic system control box and cable rack in server room were completed and labeled by the electrical contractor. National grid connected utility pole to duct bank, the building is now on a permanent power source.
Are we on time? Yes
Are we on budget? Yes
Next Steps: Work continues on the interior and exterior of the building. The committee is working with ACG and Chief Bukunt on FF&E procurement items.
January 2019
December 2018
December saw 4 days of weather impact and with the average temperature being 35 degrees, Page Construction began providing temporary heat on December 17. Excavation and installation of the septic tank and pump chamber is in progress. Excavation and back fill for the carport foundations were completed as well. Carpenters framed interior openings for duct work. They completed the installation of interior blocking, anchor bolts, hurricane clips, and interior door frames. Gypsum board was installed on some walls above finished ceiling and in the mechanical room. Vinyl siding installation is ongoing. Foam insulation was applied and painted with intumescent paint at the underside of the sloped roof. Belcour roofing repaired a wrinkled vapor barrier on the lop slope roof. EPDM membrane was installed. Installation of roof edge flashing and flashing at equipment curbs and penetrations in ongoing. Bello painting applied fire-retardant paint to plywood panel boards and painted walls of the electrical room. Rust Fire Protection began installation of fire sprinkler piping and heads in the attic and first floor, this work is ongoing. Araujo Brothers plumbing installed underground waste pipe to septic tank. Installation of waste and domestic water supply piping,hangars and sink carriers in ongoing. Thomas Snowden obtained a hot work permit for the HVAC and installed 9 VRF units,control unit and gas fired heaters. Installation of duct work, refrigerant piping, condensate drain piping and hangar/supports is ongoing. MV Electric installed conduit, work boxes, MC cable and service to temporary heaters. Security vendor and cabling vendor are now engaged in the project. Weekly project meetings are held with the Project Management Team, Design Team and the General Contractor.
Are we on time? Yes
Are we on budget? Yes
Next Steps: Work continues on the interior and exterior of the building. The committee is working with ACG and Chief Bukunt
on the Security System and other FF&E procurement items.
November 2018
Above average precipitation did have a slight impact on the schedule, rain occurred on ten working days of the project. East and West parking areas were excavated and backfilled. Columbia Gas, thanks to the help of Senator Timilty and Representative Galvin, committed to installing the gas main on 11/26, but cancelled pending a PE’s certification of the plan. At the time of this report, there was not a timeline for that. National Grid is in the process of scheduling installation of the electric service. Framing continued this month with the vestibule roof, interior wall framing, anchoring at shear walls and installation of blocking. The contractor installed shingles to the field of the slope roof. Roof work continues weather permitting. The Installation of interior hollow metal door frames and exterior windows is in progress. The contractor installed venting for the plumbing. The HVAC contractor installed ERV curb, exhaust vents on low sloped roof and hip roofs. Electrical rough in continues throughout. |
October 2018 |
September 2018
In September we saw a lot of progress on the project. The slab was poured and a few walls went up. Final decisions on materials were made including siding, paint, lockers, and flooring. These items are being ordered, with special attention to items with a long lead time. Weekly project meetings are held with the Project Management Team, Design Team and the General Contractor.
Are we on time? Yes
Are we on budget? Yes
Next Steps: Coordination with National Grid and Columbia Gas continues to be a priority. Working to make the building weather tight before winter is ongoing. |